The Hall kitchen refit has now been completed following much planning and discussion with users and it is absolutely fabulous!

The Parish Hall Chair commented "It was a total joy to work with a true professional who cared greatly about customer care and satisfaction along with providing great value for money. Our hall kitchen is now a warm and inviting place to be and a huge thank you to John, our MRFIXIT."

The Parish Hall team said "We're delighted to be able to complete this wonderful kitchen refit which will really improve the use of the Hall and be a delight for users. Not just for our Hall events but for all of you too - family events, local groups and organisations. Thank you to the Hall class users who were happy to use the main hall during the kitchen refit - despite a little disruption, and to those who weren't able to hold events at the Hall during the refit. We look forward to welcoming you as soon as you're ready."

Huge thanks to our fitter, John, MRFIXIT, who we have no hesitation in recommending. He was ably assisted by the electrician, Ben, from Twin Peaks Electrical. and the plumber, Tim'll Fixit.

John, MRFIXIT, said "Awesome few weeks working along with Viv and Geraldine of Stoodleigh Parish Hall. The remit was a total revamp of the very tired old kitchen. We gutted the kitchen, installed a liquid DPM, and levelled the floor, installed new vinyl flooring, before installing a complete new kitchen. We then concluded with decorations and new vinyl to the hallway. All in all a great few weeks."

The kitchen is now ready to share and available to hire and use by our local and wider community. Just contact the treasurer, Janet, on rusianjan@btinternet.com .

We took photos of the work along the way and you can see the kitchen - from start to finish - in the pictures as you scroll down the page below. Please have a peak at the kitchen when you're next at the Parish Hall and see for yourself!

 

Clearing of the old kitchen by Hall team and volunteers : 13 January

Clearing of the old kitchen

 

Not much left in the old kitchen - thanks to our volunteers: 13 January

Not much left in the old kitchen

 

Last items left to be removed:  13 January

Old kitchen almost empty

 

Day 1 - Welcome MrFixit, the professional, who starts today and deals with the last items - just the flooring to go now:  16 January

Almost empty

 

The first level of flooring goes down .... and we leave it to dry:  16 January

Day 1 and the first floor prep goes down

 

The second floor preparation goes down now ..... and we leave it to dry: 17 January

Second floor prep goes down

 

The third flooring prep has hardened so we're ready to start the next phase: 19 January 

Third floor prep has hardened so we're ready to start the next phase

 

Mr Fixit says "Cracking start this week, kitchen stripped out, liquid DPM and latex floor leveller down. First fix all starting today with Twin Peaks Electrical on site." 19 January

Ready for the first fixes by the electrician

 

First fix electrics completed - thank you Twin Peaks Electricals:  20 January

First fix electrics completed

 

Great start to the week - Vinyl laid and new units going:  Monday 23 January

Vinyl laid and new units going in

 

And the kitchen work has continued during the week: Friday 27 January

Kitchen work continues

 

New kitchen takes further shape this week:  Friday 27 January

Kitchen work carries on

 

Ongoing works continue:  Friday 27 January 

Ongoing work:  Friday 27 January

 

Electrician does second fix and on come the lights:  2 February

Second electrical fix and on come the lights: 2 February

 

The plumber, Tim'll Fixit, joins the team today as the kitchen nears completion: 2 February

The kitchen is almost ready to land:  2 February

 

Mr Fixit says "Penultimate day at Stoodleigh Parish Hall. Looking forward to a smooth handover tomorrow with some minor decoration works to complete, some flooring to the hallway and we should be ready to roll. Big shout out to Twin Peaks Electrical and Tim'll Fixit plumbing for their super support on this project:  2 February

Almost there and the kitchen fitter will be putting all the finishing touches tomorrow:  2 February

 

And here are the final pictures .........

Kitchen refitted

 

Kitchen refitted

 

Kitchen refitted

 

Kitchen refitted

 

Kitchen refitted

 

Come and have a look soon ...... and please share and use this new and wonderful community facility for your next event or celebration.